Fire Alarm, Intercom & Clock Replacement
Phase I
Construction Documents: Completed
Construction Duration: Summer - Fall 2014
Project Budget: $8.8 Million
Project Summary:
Removal and replacement of Fire Alarm, Intercom & Clock systems at the following nine (9) school sites. Original project scope included ceiling and light fixture replacement was revised due to DSA scoping issues.
- Addams E.S.
- Bryant E.S.
- Lee E.S
- Lincoln E.S.
- McKinley E.S.
- Rogers M.S.
- Stephens M.S.
- Washington M.S.
- Willard E.S.
Phase II
Construction Duration: June 2015 - June 2016
Project Budget: $12.6 Million
Project Summary:
Removal and replacement of Fire Alarm, Intercom & Clock systems at the following 11 school sites:
Bid Package I A:
Bid Package II B:
Bid Package III B:
- Bixby
- Kettering
- Cleveland
Bid Package IV B:
Bid Package V B:
- International ES
- Lindbergh
- Robinson
Phase III
Construction Duration: Spring-Winter 2017
Project Budget: $5.8 Million
Project Managers: John Whitmore and Alex Main
Architect: Ghataode Bannon Architects
Project Summary:
Complete fire alarm system replacement for six campuses:
- Burcham K-8
- Cubberly K-8
- King ES
- MacArthur ES
- Marshal MS
- Monroe K-8 (Personnel Commission)
Phase IV
Project Budget: $6 Million
Project Summary:
Removal and replacement of Fire Alarm, Intercom & Clock systems at the following school sites:
- Alvarado ES
- Burbank ES
- Burnett ES
- Carver ES
- Grant ES
- Harte ES
- Henry K-8
- Twain ES
Additional Information:
- Project Specs

- Project Update - Phase 5 (May 19, 2021)

- Project Update - Phase 5 (January 27, 2021)

- Project Update - Phase 5 (September 23, 2020)

- Project Update - Phase 5 (May 6, 2020)

- Project Update - Phase 4 and 5 (January 16, 2020)

- Project Update - Phase 2, 4 and 5 (September 19, 2019)

- Project Update - Phase 4 and 5 (April 11, 2019)

- Project Update - Phase 3, 4 and 5 (January 24, 2019)

- Project Update - Phase 3, 4 and 5 (September 27, 2018)

- Project Update - Phase 3 (April 19, 2018)

- Project Update - Phase 4 (April 19, 2018)

- Project Update - Phase 2 (January 18, 2018)

- Project Update - Phase 3 (January 18, 2018)

- Project Update - Phase 4 (January 18, 2018)

- Project Update - Phase 2 (September 21, 2017)

- Project Update - Phase 3 (September 21, 2017)

- Project Update - Phase 4 (September 21, 2017)

- Project Update - Phase 1 (April 27, 2017)

- Project Update - Phase 2 (April 27, 2017)

- Project Update - Phase 3 (April 27, 2017)

- Project Update - Phase 4 (April 27, 2017)

- Project Update - Phase 1, 2, 3 and 4 (January 19, 2017)

- Project Update - Phase 1 and 2 (September 22, 2016)

- Project Update - Phase 2 (April 7, 2016)

- Project Update - Phase 2 (January 21, 2016)

- Project Update - Phase 2 (September 24, 2015)

- Project Update - Phase 2 (June 25. 2015)

- Project Update - Phase 1 and 2 (March 26. 2015)

- Project Update - Phase 1 and 2 (Dec 18, 2014)

- Project Update - Phase 1 and 2 (Sep 25, 2014)

- Project Update - Phase 1 (June 26, 2014)

- Project Update - Phase 2 (June 26, 2014)