School Bond Projects Timeline* - PHASES 5-8

*Phases and dates are subject to change.

Jump to: HVAC/Modernization | Track & Field | Aquatic Center & Natatorium | New Construction | LBUSD School Bond Programs Home Page

 

Host Sites for Schools Undergoing HVAC/Modernization

HOST SITE SCHOOL/GRADE LEVELS RELOCATING  
Phase 5
(2020-2021)
Phase 6
(2021-2022)
Phase 7
(2022-2023)
Phase 8
(2023-2024)
PHASES 
9-13 »
KETTERING ES Fremont ES
Grades 3-5
Bryant ES
Grades 3-5
    »
RILEY ES Madison ES
Grades 3-5
      »
WEBSTER ES       Birney ES
Grades 3-5
»
TWAIN ES     Bancroft Grade 6   »
MONROE SITE Cubberley K-8
Grades 6-8
    Emerson ES
Grades 3-5
»
INTERIM HOUSING
NORTH
  Hughes MS
Grades 7, 8
    »
BUTLER SITE Robinson K-8
All Grades
    »
COMPLETE ONSITE
RELOCATION
Wilson HS Avalon K-12
Lakewood HS Gym
Twain ES
Wilson HS
Avalon K-12
Holmes ES
Lakewood HS Gym
Avalon K-12
Gompers ES
Stanford MS Portables
Wilson HS Gym
»

Back to: [top of page]

All Weather Turf and Field

Phase 5
(2020-2021)
Phase 6
(2021-2022)
Phase 7
(2022-2023)
Phase 8
(2023-2024)
PHASES
9-15 »

Millikan HS

 

Lakewood HS

Avalon K-12

Avalon K-12

 

Back to: [top of page]

New Aquatic Center and Natatorium Modernization

Phase 5
(2020-2021)
Phase 6
(2021-2022)
Phase 7
(2022-2023)
Phase 8
(2023-2024)
PHASES
9-15 »

 

 

 

Wilson HS

Lakewood HS

 

Back to: [top of page]

New Construction/Modernization

Phase 5
(2020-2021)
Phase 6
(2021-2022)
Phase 7
(2022-2023)
Phase 8
(2023-2024)
PHASES
9-15 »

Jordan HS - Phase 4

 

Jordan HS - Phase 2B

Lowell ES - Portable Replacement

Hamilton MS Gym

Jordan HS - Phases 2B & 3

Keller MS Locker Rooms

Jordan HS - Phases 5 & 6

 

Back to: [top of page]