Wilson Classical High Accessibility and Modular Building Installation

Accessibility Improvements - Phase 1

Project Budget: $500,000
Construction Duration: Summer 2014 - Summer 2015

Completed

Overview:
Construction of a unisex restroom, ramps, installation of two portable wheelchair lifts at the natatorium, replacement of two drinking fountains, and pathways for accessibility. Construction also includes parking lot improvements, new directional signage and minor electrical work.

 

Additional Information:

Modular Building Installation - Phase 1A

Project Budget: $1.5M
Construction Duration: Summer 2014 - Summer 2015

Completed

Overview:
Installation of 4 modular buildings (2 new restrooms, 1 ticket booth and 1 concessions building). Construction to also include new ramps and stairs for accessibility, a new service loading driveway, ground improvements, utilities extension and paving work for the stadium.

 

Additional Information:

 

Accessibility Improvements - Phase 2

Project Budget: $3.8 Million
Construction Duration: February 2016 - Winter 2017

Completed

Overview:
Construction of new modular ramps and platforms for accessible seating at visitor and home side bleachers, new telescoping bleachers and wheelchair lift at natatorium, upgrade existing restrooms for accessibility and repaving and repainting of basketball courts.

 

Additional Information: