Stephens Middle School Site Improvements

Stephens Middle School completed portables

Project Budget: $1.5 Million
Construction Starts: Summer 2019
Projected Opening: July 2020

Completed

Overview:

  • Demolition of existing modular building in its entirety
  • Addition of six (6) classroom portables including ramps
  • Utility and accessibility upgrades
  • Interior and Exterior Finishes upgrades

 

Additional Information:

 

Completed portables at Stephens Elementary School

 

Location:
1830 W Columbia St
Long Beach, CA 90810

Project Manager Planning:
Elston Soares

Project Manager Construction:
Tari Fowler

Construction Manager:
Cumming Corp.

Architect:
NAC Architecture

Contractor:
Incotechnic, Inc.