Sato Academy of Mathematics and Science (New Building)

Science Building

Project Budget: $20 Million
Construction Starts: Summer 2018
Projected Opening: Summer 2019
Square Footage: 25,000

Sato Academy in Long Beach

Overview:

A new science building with 16 classrooms and labs will accommodate 11th and 12th grade experiments and studies in the small high school's biomedical and engineering academies.

Existing buildings 200 and 300 will then be demolished, while 400 will be repurposed for storage. These changes will complete the conversion of the former middle school campus into a specialized small high school.

 

Additional Information:

 

Sato Academy New Buidling

 

Location:
1100 Iroquois Avenue
Long Beach, CA 90815

Project Manager Planning:
Jackie Roberts

Project Manager Construction:
Jacob Keaton

Construction Manager:
Jacobs

Architect:
PBK Architects

Contractor:
Erickson-Hall