Phase 1B Summer 2014-2017
Demolition of four building in north campus and addition of 53 new portable modules (including 48 classrooms). Construction of three new classroom buildings J (1100), K (1200), and L (1300).
Additional Information:
- Public Meeting Presentation (January 24, 2017)

- Construction Activities Update (June 30, 2017)

- Construction Activities Update (June 9, 2017)

- Construction Activities Update (April 27, 2017)

- Construction Activities Update (March 10, 2017)

- Construction Activities Update (February 17, 2017)

- Construction Activities Update (February 3, 2017)

- Construction Activities Update (January 20, 2017)

- Construction Activities Update (December 16, 2016)

- Construction Activities Update (December 2, 2016)

- Construction Activities Update (November 11, 2016)

- Construction Activities Update (September 30, 2016)

- Construction Activities Update (September 16, 2016)

- Construction Activities Update (August 5, 2016)
- Project Specs - Construction

- Project Specs - Demolition

- Project Update (January 19, 2017)

- Project Update (September 22, 2016)

- Project Update (April 7, 2016)

- Project Update (January 21, 2016)

- Project Update (September 24, 2015)

- Project Update (June 25, 2015)

- Project Update (March 26, 2015)

- Project Update (December 18, 2014)

- Project Update (November 18, 2014)

- Project Update (September 25, 2014)

- Project Update (August 19, 2014)

- Jordan High Planned Renovation

- Project Update (June 26, 2014)

- CEQA Notice of Public Hearing Final EIR (November 2013)
-
CEQA Notice of Availability Draft Environmental Impact Report
(September 2013)

- Jordan High School Major Renovation Project Initial Study (July 2013)

- Community Meeting Presentation (February 28, 2013)

- Houghton Park Joint Use (August 17, 2012)

- Community Meeting Presentation (July 10, 2012)

TOP
Phase 1C 2017-2019
Demolition of one building and portables, construction of Buildings M (7000) and N (8000).
Phase 1D 2017-2018
Renovation of Band Building 2000
Phase 2A Summer 2018-2020
Project Budget: $19.5 Million
Square Footage: 21,000
Renovation of Administration Building 1000 and Library Building 9000.
Additional Information:
- Project Update (January 27, 2021)

- Project Update (September 23, 2020)

- Project Update (May 6, 2020)

- Project Update (January 16, 2020)

- Project Update (September 19, 2019)

- Project Update (April 11, 2019)

- Project Update (January 24, 2019)

- Project Update (September 27, 2018)

- Project Update (April 19, 2018)

- Project Update (January 18, 2018)

- Project Update (September 21, 2017)

- Project Update (January 19, 2017)

Phase 2B 2021-2023
Project Budget: $36.8 Million
Square Footage: 62,000
Demolition of four buildings, construction of Buildings B (200) and C (300).
Additional Information:
- Project Update (January 27, 2021)

- Project Update (September 23, 2020)

- Project Update (May 6, 2020)

- Project Update (January 16, 2020)

- Project Update (September 19, 2019)

- Project Update (April 11, 2019)

- Project Update (January 24, 2019)

- Project Update (September 27, 2018)

- Project Update (April 19, 2018)

- Project Update (January 18, 2018)

- Project Update (September 21, 2017)

- Project Update (January 19, 2017)

TOP
Phase 3 2022-2023
Project Budget: $5.1 Million
Square Footage: 50,655
Renovation of existing Science Buidling 1000
Additional Information:
Phase 4 2017-2020
Project Budget: $22 Million
Square Footage: 41,000
Seismic upgrades to auditorium, access compliance, fire/life safety improvements and renovation/repair of infrastructure.
Additional Information:
- Notice of Public Meeting

- Project Update
(January 27, 2021)
- Project Update
(September 23, 2020)
- Project Update
(May 6, 2020)
- Project Update
(January 16, 2020)
- Project Update
(September 19, 2019)
- Project Update
(April 11, 2019)
- Project Update
(January 24, 2019)
- Project Update
(September 27, 2018)
- Project Update
(April 19, 2018)
- Project Update
(January 18, 2018)
- Project Update
(September 21, 2017)
- Project Update
(January 19, 2017)
- Project Update
(September 22, 2016)
- Project Update
(April 7, 2016)
- Project Update
(January 21, 2016)
- Project Update
(September 24, 2015)
- Project Update
(June 25, 2015)
- Project Update
(March 26, 2015)
- Project Update
(December 18, 2014)
- Project Update
(June 26, 2014)
Phase 5 2025-2026
Project Budget: $18.3 Million
Construction of new bleachers/stadium and athletic fields.
Additional Information:
- Project Update (January 27, 2021)

- Project Update (September 23, 2020)

- Project Update (May 6, 2020)

- Project Update (January 16, 2020)

- Project Update (September 19, 2019)

- Project Update (April 11, 2019)

- Project Update (January 24, 2019)

- Project Update (September 27, 2018)

- Project Update (April 19, 2018)

- Project Update (January 18, 2018)

- Project Update (September 21, 2017)

- Project Update (January 19, 2017)

TOP
Phase 6 2023-2025
Project Budget: $14 Million
Square Footage: 62,000
Conversion of natatorium into gymnasium and construction of outdoor swimming pool.
Additional Information:
- Project Update (January 27, 2021)

- Project Update (September 23, 2020)

- Project Update (May 6, 2020)

- Project Update (January 16, 2020)

- Project Update (September 19, 2019)

- Project Update (April 11, 2019)

- Project Update (January 24, 2019)

- Project Update (September 27, 2018)

- Project Update (April 19, 2018)

- Project Update (January 18, 2018)

- Project Update (September 21, 2017)

- Project Update (January 19, 2017)

Applicable District-wide Projects