Building on Success LBUSD Campus Improvement Bonds

Fire Alarm, Intercom & Clock Replacement

Phase I

Construction Documents: Completed
Construction Duration: Summer - Fall 2014
Project Budget: $8.8 Million

Completed

Project Summary:

Removal and replacement of Fire Alarm, Intercom & Clock systems at the following nine (9) school sites. Original project scope included ceiling and light fixture replacement was revised due to DSA scoping issues.

  • Addams E.S.
  • Bryant E.S.
  • Lee E.S
  • Lincoln E.S.
  • McKinley E.S.
  • Rogers M.S.
  • Stephens M.S.
  • Washington M.S.
  • Willard E.S.

Phase II

Construction Duration: June 2015 - June 2016
Project Budget: $12.6 Million

Project Summary:

Removal and replacement of Fire Alarm, Intercom & Clock systems at the following 11 school sites:

    Bid Package I A:
    • Cabrillo HS
    Bid Package II B:
    • Hudson ES
    • Webster ES
    Bid Package III B:
    • Bixby
    • Kettering
    • Cleveland
    Bid Package IV B:
    • Jefferson MS
    • Barton ES
    Bid Package V B:
    • International ES
    • Lindbergh
    • Robinson
Completed

Phase III

Construction Duration: Spring-Winter 2017
Project Budget: $5.8 Million
Project Managers: John Whitmore and Alex Main
Architect: Ghataode Bannon Architects

Project Summary:

Complete fire alarm system replacement for six campuses:

  • Burcham K-8
  • Cubberly K-8
  • King ES
  • MacArthur ES
  • Marshal MS
  • Monroe K-8 (Personnel Commission)

 

Phase IV

Project Budget: $6 Million

Project Summary:

Removal and replacement of Fire Alarm, Intercom & Clock systems at the following school sites:

  • Alvarado ES
  • Burbank ES
  • Burnett ES
  • Carver ES
  • Grant ES
  • Harte ES
  • Henry K-8
  • Twain ES

 

Additional Information:

 

fire alarm

 

Architect:
CSDA Architects, and
Westburg+White, Inc.

Contractor:
Minco Construction and JAM Corporation

Last Modified: 5/29/2017