School Bond Projects Timeline*

*Phases and dates are subject to change.

Jump to: HVAC/Modernization | Track & Field | New Construction | LBUSD School Bond Programs Home Page

 

Host Sites for Schools Undergoing HVAC/Modernization

HOST SITE SCHOOLS/GRADE LEVELS RELOCATING
Phase 1
(2017)
Phase 2
(2017-2018)
Phase 3
(2018-2019)
Phase 4
(2019-2020)
Phase 5
(2020-2021)
go to phases 6 - 15

KETTERING ES

Interim Housing Installed

Kettering ES (2018)
(stays on site)

Mann ES Grades 3-5
(2018-2019)

Naples ES Grade 3-5
(2019-2020)

Fremont ES
Grades 3-5
(2020-2021)

 

RILEY ES

Interim Housing Installed

Riley ES (2018)
(stays on site)

Longfellow ES
Grades 3-5

(2018-2019)

 

Madison ES
Grades 3-5

(2020-2021)

 

WEBSTER ES

Interim Housing Installed

 

Webster ES
(2018-2019)
(stays on site)

Muir K-8 Grades 3-5
(2019-2020)

 

 

ROGERS MS

Interim Housing Installed

Rogers MS (2018)
(Grades 6 & 7 stay on site; Grade 8 to Browning )

Lowell ES Grades 3-5 (2018-2019)

 

 

 

PRISK ES

 

 

 

 

Prisk ES (2020-2021)
(stays on site)

 

MONROE SITE

 

Cleveland ES
Grades 3-5
(2018)

McKinley ES
Grades 3-5
(2018-2019)

 

Cubberley K-8
Grades 6-8

(2020-2021)

 
JORDAN PLUS

 

Stephens MS
All Grades
(2018)

 

     
BUTLER SITE

 

 

Jefferson Leadership Academies All Grades
(2018-2019)

Alvarado ES
(2019-2020)

   

COMPLETELY ONSITE RELOCATION

 

Garfield ES (2018)

 

Barton ES (2018-2019)

Burcham ES
(2018-2019)

Keller MS (2018-2019)

Lakewood HS
(2018-2020)

Lindsey MS
(2018-2019)

MacArthur ES
(2018-2019)

Bixby ES Grades 3-5
(2019-2020)

Wilson HS (2020-2022)

 

Back to: [top of page]

All Weather Turf and Field

Phase 1 (2017) Phase 2 (2017-2018) Phase 3 (2018-2019) Phase 4 (2019-2020) Phase 5 (2020-2021) go to phases 6 - 15

Cabrillo HS (2017-2018)

Wilson HS (2017-2018)

Polytechnic HS (2017-2018)

 

Jefferson Leadership Academies (2018-2019)

Rogers MS (2018-2019)

Stephens MS (2018-2019)

 


 

Millikan HS (2020-2021)

 

 

Back to: [top of page]

New Construction/Modernization

Phase 1 (2017) Phase 2 (2017-2018) Phase 3 (2018-2019) Phase 4 (2019-2020) Phase 5 (2020-2021) go to phases 6 - 15

Educare (2017-2018)

Jordan HS (started 2017)

Renaissance HS
(2017-2018)

 

 

Millikan HS - Building 1000
(2018-2019)

Sato Academy (2018-2019)

 

 

 

Back to: [top of page]